Subject: GTV weekly status update
Mime-Version: 1.0
Content-Type: text/plain; charset=ANSI_X3.4-1968
Content-Transfer-Encoding: 7bit
X-From: Zhiyong Wei <Zhiyong Wei/ENRON@enronXgate@ENRON>
X-To: Louise Kitchen <Louise Kitchen/HOU/ECT@ECT>, Colleen Sullivan <Colleen Sullivan/HOU/ECT@ECT>, Geoff Storey <Geoff Storey/ENRON@enronXgate>, Philippe A Bibi <Philippe A Bibi/ENRON@enronXgate>, Beth Perlman <Beth Perlman/ENRON@enronXgate>, Stephen Stock <Stephen Stock/ENRON@enronXgate>
X-cc: 
X-bcc: 
X-Folder: \ExMerge - Kitchen, Louise\'Americas\IT
X-Origin: KITCHEN-L
X-FileName: louise kitchen 2-7-02.pst

Below please find the GTV project status update for this week. Project timeline update is also included in the attached file.

GTV status meeting attendees:  Zhiyong Wei, Dave Nommensen, Russ Severson, Francis Lim, Jeremy Wong, Bill Fortney, Chuck Ames, Geoff Storey, Karima Husain, Jay Krish.

Accomplishments:
?	Incorporating physical deal positions in TDS:
o	Changes for the view aggregation have been completed (please see the attached project timeline).
o	Provided Group of Groups and filters for Cash Position tab.

?	Single point of deal entry for term deals:
o	Single point of deal entry for term deals is in user test.

?	Gas Daily deals:
o	Changes to PortCalc application to create GDI calc in ERMS have been in user testing and some further revisions are requested.

?	Live feeds for Gas Daily/intra-month curves:
o	Released to production.

?	Option Grid (phase 2):
o	Released to production.

?	Gas Daily options (phase 2):
o	Changes to PortCalc application have been completed and in user test.
o	The Option Delta Change Forward Month report has been completed and in user test.

Plans for the week ending 5/18/01:
?	Continue IT development of Phase I items.
o	Changes to introduce expandable total in cash position tab.
o	Changes to PortCalc for valuing physical future month positions.
o	Some modification to GDI Calc.

?	Continue IT development of Phase II issues.

Issues / Open Items:
None


 
Thanks

Zhiyong